  1. A can finish a job in 6 days and B in 12 days. If they work on alternate days, starting with A, in how many days will the job be finished?

    8 days. With 12 units of work, A does 2 units a day and B 1. Every 2-day cycle does 3 units, so 4 cycles (8 days) finish exactly 12 units.