- 12 men can finish a job in 18 days working 8 hours a day. How many days will 16 men take working 9 hours a day?
12 days. Total work in man-hours = 12 x 18 x 8 = 1,728. With 16 men at 9 hours a day, daily output = 144 man-hours, so days = 1,728 / 144 = 12.