A can do a job in 20 days. A works alone for 4 days, then B joins and together they finish the rest in 6 days. How long would B take alone?

SHORT ANSWER

12 days. A works all 10 days and does 10/20 = half the job. B does the other half in 6 days, so B alone would need 12 days.

Explain it simply

Track each person's own working days separately. A was there from start to finish, 4 + 6 = 10 days. B was there only for the last 6 days. Work done by each person is their rate times their own days. The two pieces add up to one whole job.

Example

Question: A alone takes 20 days. A works 4 days alone, then A + B finish in 6 more days. B alone?

  1. A works 4 + 6 = 10 days in total. A's work = 10/20 = 1/2.
  2. B's work = 1 - 1/2 = 1/2, done in 6 days.
  3. B alone = 6 x 2 = 12 days.

Check with units: total 60 units. A does 3 a day, B does 5 a day. A's 4 days alone = 12 units. Then 6 days together at 8 a day = 48 units. Total 60.

js
const total = 60, a = total / 20;
const bWork = total - a * 10;
console.log(6 * (total / bWork)); // Output: 12
console.log(a * 4 + (a + 5) * 6); // Output: 60

What to say in the interview

"I count each person's own days. A works all 10 days and finishes half. B does the other half in 6 days, so B alone takes 12."

Common mistakes

  • Counting only 4 days for A.
  • Assuming B's 6 days produced the remaining work alone.

#aptitude#time-and-work

Related questions

Practise more Aptitude questions

Test your recall with short answers, then return to the detailed explanations when you need context.

Open Aptitude quick answers →

Get new questions like this by email

One short email when something new and useful lands. No spam, unsubscribe in one tap.

By subscribing you agree to the Privacy Policy.